# SB 370 - Introduced

90R3204 EMS-D

By: Cook of Harris S.B. No. 370

A BILL TO BE ENTITLED

AN ACT

relating to a study of the costs and benefits of burying distribution power lines in certain metropolitan areas.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

### SECTION 1.

DEFINITIONS. In this Act:

(1) "Commission" means the Public Utility Commission of Texas.

(2) "Study areas" means the following regions:

(A) the Austin metropolitan area;

(B) the Dallas-Fort Worth metroplex;

(C) the Houston metropolitan area; and

(D) the San Antonio metropolitan area.

### SECTION 2.

FINDINGS. The legislature finds that:

(1) during times of extreme weather, overhead distribution power lines often take on significant damage;

(2) underground distribution power lines are more resistant than overhead distribution power lines to extreme weather conditions; and

(3) the cost of burying distribution power lines is significant.

### SECTION 3.

STUDY. The commission shall evaluate in the study areas each of the following for electric cooperatives, investor-owned utilities, and municipally owned utilities:

(1) potential costs of burying existing overhead distribution power lines, including costs that could be passed on to ratepayers;

(2) potential costs of maintaining and repairing underground distribution power lines;

(3) potential cost savings associated with reduced power outages after burying distribution power lines; and

(4) anticipated effects of burying distribution power lines on the environment, such as land use and water quality, on public safety, and on emergency response.

### SECTION 4.

REPORT. The commission shall submit a report of the results of the study and any recommendations to the governor, lieutenant governor, and speaker of the house of representatives not later than December 31, 2028.

### SECTION 5.

EXPIRATION DATE. This Act expires January 31, 2029.

### SECTION 6.

EFFECTIVE DATE. This Act takes effect September 1, 2027.