# HB 587 - Introduced

90R3766 DRS-F

By: Money H.B. No. 587

A BILL TO BE ENTITLED

AN ACT

relating to the authority of a county to regulate the construction of certain industrial and offensive land use facilities.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

### SECTION 1.

Chapter 240, Local Government Code, is amended by adding Subchapter F to read as follows: <ins>SUBCHAPTER F. REGULATION OF CERTAIN INDUSTRIAL AND OFFENSIVE LAND USE FACILITIES</ins>

<ins>Sec. 240.101. DEFINITIONS. In this subchapter:</ins>

<ins>(1) "Alternative energy facility" means:</ins>

<ins>(A) a wind power facility as defined by Section 301.0001, Utilities Code;</ins>

<ins>(B) a solar power facility as defined by Section 302.0001, Utilities Code; or</ins>

<ins>(C) a battery storage facility.</ins>

<ins>(2) "Industrial facility" includes:</ins>

<ins>(A) an electric generation facility;</ins>

<ins>(B) an alternative energy facility;</ins>

<ins>(C) a manufacturing or production facility;</ins>

<ins>(D) a distribution or logistics center;</ins>

<ins>(E) a data center;</ins>

<ins>(F) a water or wastewater treatment plant; and</ins>

<ins>(G) another heavy industrial or large-scale commercial facility.</ins>

<ins>(3) "Offensive land use facility" includes a concrete plant, concrete crushing facility, landfill, solid waste transfer station, or automotive wrecking and salvage yard.</ins>

<ins>Sec. 240.102. PERMIT REQUIRED. Notwithstanding any other law, a person may not construct an industrial facility or offensive land use facility in the unincorporated area of a county unless the person obtains a permit from the commissioners court of the county.</ins>

<ins>Sec. 240.103. PERMITTING PROCEDURE. (a) A commissioners court of a county shall by order establish a procedure to review and approve an application for a permit to construct an industrial facility or offensive land use facility.</ins>

<ins>(b) A permitting procedure established under this section must require:</ins>

<ins>(1) a permit be issued by order of the commissioners court; and</ins>

<ins>(2) the commissioners court to hold at least two public hearings on the application for the permit not less than two weeks and not more than two months apart.</ins>

<ins>Sec. 240.104. DETERMINATION OF INDUSTRIAL OR OFFENSIVE LAND USE FACILITY. A commissioners court by order may determine that a facility proposed to be constructed is:</ins>

<ins>(1) an offensive land use facility; or</ins>

<ins>(2) an industrial facility, if the commissioners court by order determines that the proposed facility:</ins>

<ins>(A) will require substantial infrastructure or resources when operational; or</ins>

<ins>(B) by its nature, scale, or type of operations constitutes a facility that would be suited for location in a municipal zoning district that allows industrial use, if the project were proposed to be located in an area subject to municipal zoning regulation.</ins>

<ins>Sec. 240.105. ISSUANCE OF PERMIT. (a) In issuing a permit required by this subchapter, a commissioners court must consider:</ins>

<ins>(1) the compatibility of the proposed facility that is the subject of the permit with existing land uses in the surrounding area;</ins>

<ins>(2) the potential impact of the facility on:</ins>

<ins>(A) public health and safety;</ins>

<ins>(B) air, water, and soil quality; and</ins>

<ins>(C) local infrastructure, including roads, utilities, and emergency services;</ins>

<ins>(3) public comment and input from county residents and other stakeholders; and</ins>

<ins>(4) other factors that the commissioners court determines are relevant to balancing the interest in development and the welfare of the community.</ins>

<ins>(b) A permit issued under this section may include conditions and requirements that the commissioners court determines are necessary to mitigate potential negative effects of the proposed facility that is the subject of the permit, including a requirement that the applicant implement measures for:</ins>

<ins>(1) the protection of public health and safety, including providing necessary training and equipment for emergency services;</ins>

<ins>(2) the improvement or maintenance of local infrastructure;</ins>

<ins>(3) the protection of air, water, and soil quality; and</ins>

<ins>(4) noise reduction.</ins>

<ins>Sec. 240.106. REVOCATION OR SUSPENSION OF PERMIT. A commissioners court may revoke or suspend a permit issued under this subchapter if the commissioners court by order finds that:</ins>

<ins>(1) the permit holder has violated the terms of the permit; or</ins>

<ins>(2) the permitted project causes undue harm to the surrounding area or community.</ins>

<ins>Sec. 240.107. ENFORCEMENT. The commissioners court of a county may adopt orders to enforce this subchapter or an order adopted under this subchapter.</ins>

### SECTION 2.

This Act takes effect September 1, 2027.