Water Code § 60.462: CONTRACTS FOR FACILITIES: CONSTRUCTION MANAGER-AT-RISK
No bill in the 90th Legislature changes this section yet
Follow this section in Texas Bill Atlas: a bill filed later that changes it shows up as new.
Part of Water Code Chapter 60, with every bill that changes it.
Bills are matched to sections automatically from their text and can be missed, for example when a bill changes a whole chapter at once or renumbers sections. No bill listed here does not mean no bill changes this section.
Current law
Sec. 60.462. CONTRACTS FOR FACILITIES: CONSTRUCTION MANAGER-AT-RISK. (a) A district may award a contract to a construction manager-at-risk for the construction, rehabilitation, alteration, or repair of a facility provided that the construction manager-at-risk and the district follow the procedures prescribed by this section.
(b) Before or concurrently with selecting a construction manager-at-risk, the district shall select or designate an engineer or architect who shall prepare the construction documents for the project and who has full responsibility for complying with Chapter 1001 or 1051, Occupations Code, as applicable. If the engineer or architect is not a full-time employee of the district, the district shall select the engineer or architect in accordance with Section 2254.004, Government Code. The district's engineer, architect, or construction manager-agent for a project may not serve, alone or in combination with another, as the construction manager-at-risk.
(c) The district shall provide or contract for, independently of the construction manager-at-risk, the inspection services, the testing of construction materials, and the verification testing services necessary for acceptance of the facility by the district. The district shall select those services for which it contracts in accordance with Section 2254.004, Government Code.
(d) The district shall select the construction manager-at-risk in either a one-step or two-step process. The district shall prepare a request for proposals, in the case of a one-step process, or a request for qualifications, in the case of a two-step process, that includes general information on the project site, project scope, schedule, selection criteria, and estimated budget, the time and place for receipt of proposals or qualifications, as applicable, a statement as to whether the selection process is a one-step or two-step process, and other information that may assist the district in its selection of a construction manager-at-risk. The district shall state the selection criteria in the request for proposals or qualifications, as applicable. The selection criteria may include the offeror's experience, past performance, safety record, proposed personnel and methodology, and other appropriate factors that demonstrate the capability of the construction manager-at-risk. If a one-step process is used, the district may request, as part of the offeror's proposal, proposed fees and prices for fulfilling the general conditions.
(e) If a two-step process is used, the district may not request fees or prices in step one. In step two, the district may request that five or fewer offerors, selected solely on the basis of qualifications, provide additional information, including the construction manager-at-risk's proposed fee and its price for fulfilling the general conditions.
(f) At each step, the district shall receive, publicly open, and read aloud the names of the offerors. At the appropriate step, the district sha
The section continues: whole chapter.
Links
- This chapter as it stands now, Markdown copy of the Texas Legislative Council's statute files
- Official text on statutes.capitol.texas.gov
Texas Bill Atlas is an independent research tool, not an official state website.