Utilities Code § 34.0104: LOANS FOR ERCOT POWER REGION
1 bill in the 90th Legislature would change this section
- HB 589 amends this section
Part of Utilities Code Chapter 34, with every bill that changes it.
Bills are matched to sections automatically from their text and can be missed, for example when a bill changes a whole chapter at once or renumbers sections. No bill listed here does not mean no bill changes this section.
Current law
Sec. 34.0104. LOANS FOR ERCOT POWER REGION. (a) The commission may use money in the fund without further appropriation to provide loans to finance upgrades to existing dispatchable electric generating facilities providing power for the ERCOT power region that result in a net increase of at least 100 megawatts of capacity for each facility or the construction of dispatchable electric generating facilities providing power for the ERCOT power region that each have a generation capacity of at least 100 megawatts. For the purposes of this section, a generating facility is considered to be dispatchable if the facility's output can be controlled primarily by forces under human control. An electric energy storage facility is not eligible for a loan under this section.
(b) The commission may provide a construction loan under this section only:
(1) for construction of a facility that will have a generation capacity of at least 100 megawatts and that does not meet the planning model requirements necessary to be included in the Capacity Demand and Reserves Report of the independent organization certified under Section 39.151 for the ERCOT power region before June 1, 2023;
(2) in an amount that does not exceed 60 percent of the estimated cost of the facility to be constructed; and
(3) if the agreement ensures that the loan is to be the senior debt secured by the facility.
(b-1) Notwithstanding Subsection (b)(3):
(1) a construction loan provided to a municipally owned utility, or an instrumentality of a municipal corporation established for the benefit of a municipally owned utility, may be in the form of a public security, as defined by Section 1201.002, Government Code, issued by the loan applicant if the public security is payable on a parity basis with other debt of the loan applicant secured by a senior lien on net revenues of the facility or the loan applicant's utility system; and
(2) a construction loan provided to an electric cooperative may be secured by a senior lien on substantially all electric system assets of the electric cooperative, including the facility for which the loan is provided, payable on a parity basis with other debt of the loan applicant secured by a senior lien.
(c) The commission shall evaluate an application for a loan under this section based on:
(1) the applicant's:
(A) quality of services and management;
(B) efficiency of operations;
(C) history of electricity generation operations in this state and this country;
(D) resource operation attributes;
(E) ability to address regional and reliability needs;
(F) access to resources essential for operating the facility for which the loan is requested, such as land, water, and reliable infrastructure, as applicable; and
(G) evidence of creditworthiness and ability to repay the loan on the terms established in the loan agreement, including the applicant's total assets, total liabilities, net worth, and credit ratings issued by major credit rating agencies;
(2) the gene
The section continues: whole chapter.
Links
- This chapter as it stands now, Markdown copy of the Texas Legislative Council's statute files
- Official text on statutes.capitol.texas.gov
- RSS feed of actions on these bills
Texas Bill Atlas is an independent research tool, not an official state website.