Current law
Sec. 201.061. EXEMPTION FOR GAS PRODUCED THAT WOULD OTHERWISE HAVE BEEN VENTED OR FLARED. (a) In this section:
(1) "Commission" means the Railroad Commission of Texas.
(2) "Qualifying well" means a well that:
(A) is connected to a pipeline on which pipeline takeaway capacity is not expected to meet the demand for gas produced from the well;
(B) is not connected to a pipeline and for which connection to a pipeline is technically or commercially unfeasible but is operated by a well operator who has contractually dedicated the well, the gas produced from the well, or the land or lease on which the well is located to a pipeline operator; or
(C) is not connected to a pipeline and is operated by a well operator who has not contractually dedicated the well, the gas produced from the well, or the land or lease on which the well is located to a pipeline operator.
(3) "Well operator" means the person responsible for the actual physical operation of an oil or gas well.
(b) Gas produced from a qualifying well that is consumed within 1,000 feet of the qualifying well and would otherwise have been lawfully vented or flared is not subject to the tax imposed by this chapter.
(c) A well operator and a pipeline operator, as applicable, may apply to the commission in the manner provided by Subsection (d), (e), or (f), as applicable, for certification that a well is a qualifying well.
(d) An application that relates to a well described by Subsection (a)(2)(A) must:
(1) include an attestation that pipeline takeaway capacity is not expected to meet the demand for gas produced from the well;
(2) be submitted jointly by the well operator and the pipeline operator; and
(3) certify that the commission authorized gas from the well to be flared for at least 30 days during the year preceding the year in which the application is filed.
(e) An application that relates to a well described by Subsection (a)(2)(B) must:
(1) attest that:
(A) the well is not connected to a pipeline; and
(B) it is technically or commercially unfeasible to connect the well to a pipeline;
(2) be submitted jointly by the well operator and the pipeline operator; and
(3) certify that the commission authorized gas from the well to be flared for at least 30 days during the year preceding the year in which the application is filed.
(f) An application that relates to a well described by Subsection (a)(2)(C) must:
(1) attest that the well:
(A) is not connected to a pipeline; and
(B) is operated by a well operator who has not contractually dedicated the well, the gas produced from the well, or the land or lease on which the well is located to a pipeline operator;
(2) be submitted by the well operator; and
(3) certify that the commission authorized gas from the well to be flared for at least 30 days during the year preceding the year in which the application is filed.
(g) The commission may require an applicant described by Subsection (c) to provide the commission with any information t
The section continues: whole chapter.
Links
- This chapter as it stands now, Markdown copy of the Texas Legislative Council's statute files
- Official text on statutes.capitol.texas.gov
- RSS feed of actions on these bills
Texas Bill Atlas is an independent research tool, not an official state website.