Transportation Code § 254.009: DRAINAGE SYSTEM SURVEY
No bill in the 90th Legislature changes this section yet
Follow this section in Texas Bill Atlas: a bill filed later that changes it shows up as new.
Part of Transportation Code Chapter 254, with every bill that changes it.
Bills are matched to sections automatically from their text and can be missed, for example when a bill changes a whole chapter at once or renumbers sections. No bill listed here does not mean no bill changes this section.
Current law
Sec. 254.009. DRAINAGE SYSTEM SURVEY. (a) After approval of a petition under Section 254.004, the commissioners court shall hire a surveyor to conduct a survey under this section for an amount determined by the court at the same meeting or at a subsequent term of court. The surveyor must be an engineer.
(b) The survey shall be applied first to the first-class roads, followed by the second-class and third-class roads.
(c) The surveyor shall make the survey and system of levels required by this section as soon as practicable after the surveyor is employed.
(d) The surveyor shall:
(1) run a line of levels along the county's public roads, measure the roads from beginning to end, and measure the distance of each waterway crossed by a public road from the location of the beginning of the waterway;
(2) place stakes or monuments along the line at intervals of 100 feet, with intermediate stakes that may be necessary, numbered progressively;
(3) establish permanent benchmarks along the line at intervals of one mile or less as necessary;
(4) establish by stakes or monuments different in character and appearance from all other stakes or monuments the highest point on the road between each of the natural waterways crossed by the road;
(5) measure and establish by suitable marks the frontage of each tract of real property abutting the road; and
(6) if there is a natural waterway adjacent to the line of the road and ditch and the waterway is necessary as an outlet for the water at any point on the ditch, measure the distance to the waterway and run the line of levels to the waterway at the nearest practicable point on the road and ditch.
(e) The surveyor shall prepare a map showing:
(1) the location of the ditch or ditches, with the position of stakes or monuments with numbers corresponding with those on the ground;
(2) the location of benchmarks with their elevations referred to an assumed or previously determined datum; and
(3) the lines and boundaries of adjacent property and the courses and distances of any adjacent watercourse, with a profile of the line of the ditch showing the assumed datum and the grade line of the bottom of the ditch, and the elevation of each stake, monument, or other important feature along the line, such as the top of the banks, the bottom of all ditches or watercourses, the surface of the water, the top of the rail, the bottom of the tie, the foot of the embankment, and the bottom of each borrow pit of each railroad.
(f) The map or an explanation accompanying the map must:
(1) give in tabular form the depth of the cut and the width at the bottom, at the top, at the source, at the outlet, and at each 100-foot stake or monument to the ditch;
(2) show the total number of cubic yards of earth to be excavated and removed from the ditch between each natural waterway into which the water is to be conveyed;
(3) show an estimate of the cost of each portion of each ditch located between natural waterways crossed by the road;
The section continues: whole chapter.
Links
- This chapter as it stands now, Markdown copy of the Texas Legislative Council's statute files
- Official text on statutes.capitol.texas.gov
Texas Bill Atlas is an independent research tool, not an official state website.