HB 730: Relating to the interconnection of large load customers and the recovery of costs of generation facilities serving large load customers by electric utilities operating outside of the ERCOT power region.
- Session
- 90th Texas Legislature, Regular Session
- Status
- Filed
- Filed
- Nov 9, 2026
- Most recent action
- 11/09/2026 H Filed
- Authors
- Perez, Vincent
- Official subjects
- Utilities--Electric; PUBLIC UTILITY COMMISSION
AI summary (not official): Limits when utilities can charge other customers for generation serving a large-load customer and requires large-load interconnection standards.
Topics: Energy & utilities, Business regulation. From AI review or caption rules.
Agencies it could affect (possible, not confirmed): Public Utility Commission of Texas. From AI review or caption rules.
Laws this bill changes
- amends Utilities Code § 36.053
- amends Utilities Code § 37.056
- amends Utilities Code chapter 39
- adds Utilities Code § 39.411
Bill text (Introduced)
By: Perez of El Paso H.B. No. 730
A BILL TO BE ENTITLED
AN ACT
relating to the interconnection of large load customers and the recovery of costs of generation facilities serving large load customers by electric utilities operating outside of the ERCOT power region.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1.
Section 36.053, Utilities Code, is amended by adding Subsections (e), (f), and (g) to read as follows:
(e) In this subsection and Subsections (f) and (g):
(1) "Dedicated large load generation facility" means a generation facility, or a portion of a generation facility, that an electric utility operating solely outside of the ERCOT power region constructs, acquires, or contracts for primarily to serve one large load customer.
(2) "Large load customer" means a retail customer whose total load at a single site exceeds, or is projected to exceed, 75 megawatts. The term includes an affiliate or successor in interest of the customer.
(f) Notwithstanding Section 39.410 or any other law, the commission may not find that a dedicated large load generation facility is used by and useful to the electric utility in providing service, and the utility may not include the original cost of the facility in invested capital or otherwise recover the cost of the facility from customers other than the large load customer, unless the commission, in a proceeding for which notice is provided to each affected customer class and that is concluded before the cost is included in rates, finds that:
(1) the facility provides a net benefit to the utility's customers other than the large load customer; and
(2) the costs of the facility are allocated among customer classes in accordance with cost-causation principles and in a manner that does not cause the rates of the residential or small commercial customer classes to exceed the rates those classes would pay if the facility had not been constructed, acquired, or contracted for.
(g) The commission may make the findings described by Subsection (f) in a proceeding under Chapter 37 for a certificate of convenience and necessity for the facility or in a separate proceeding. Subsection (f) applies regardless of whether the large load customer has agreed to pay all or part of the costs of the facility for a limited period.
SECTION 2.
Section 37.056, Utilities Code, is amended by adding Subsection (j) to read as follows:
(j) The commission may not grant a certificate for a dedicated large load generation facility, as defined by Section 36.053(e), unless the commission:
(1) makes the findings described by Section 36.053(f); or
(2) conditions the certificate on the electric utility's agreement that the costs of the facility will not be recovered from customers other than the large load customer unless the commission later makes those findings in a proceeding described by Section 36.053(f).
SECTION 3.
Subchapter I, Chapter 39, Utilities Code, is amended by adding Section 39.411 to read as follows:
Sec. 39.411. INTERCONNECTION OF LARGE LOADS. (a) In this section, "large load customer" includes an entity requesting an interconnection that exceeds the demand threshold established under Subsection (c) and a successor in interest to such an entity.
The text continues: full text of HB 730.
Links
- Full bill text (Introduced), Markdown copy of the official file
- Record, history and review for AI agents
- Official bill history on Texas Legislature Online
Texas Bill Atlas is an independent research tool, not an official state website.